2021 Treatment Plant Improvements Project (CIP 20708)
The general scope of work for this project includes replacement of three polymer storage tanks; replacement of concrete tank bases; connection of tanks to existing fill, recirculation, and suction piping; construction of temporary polymer storage tank and associated piping; demolition of existing tanks and concrete bases; concrete coating; and replacement of existing ultrasonic level sensor and transmitter. Also included in the scope of work is the replacement of three 36-inch diameter butterfly diversion valves located within the treatment plant gallery.
Addendum 1
(click to expand/collapse)
Name | Size | |||
CIP 20708 - Addendum 1 | 9.7 MB |
Addendum 2
(click to expand/collapse)
Name | Size | |||
CIP 20708 - Addendum 2 | 1.9 MB |