2023 Collection System Rehabilitation Project (CIP 22701)

The general scope of work for this project included in the base bid and bid alternate is the rehabilitation and/or replacement of 4", 6", 8", 10", 12" and 18" sewer mains by the following methods: Approximately 18,900 LF by cured in place pipe (CIPP) lining, 9,200 LF by pipe bursting, and 850 LF by open cut methods. Also included in the scope of work is the rehabilitation or replacement of approximately 540 laterals and 51 sewer structures within the project area.

Status

Bidding Closed

Prebid Date11/15/22 2:00pm

Bid Date12/6/22 2:00pm

Company & Contacts

NapaSan
Michael Fitch  
707-258-6030

Location

Napa, CA

Documents

The estimated cost of construction for the Bid Schedule is $7,000,000.